Cyberport Development - Contract C1
Services M&E Installation
Location Telegraph Bay, Hong Kong
Client Cyberport Ltd.
Architect Wong Tung and Partners Limited
Consulting Engineer Ove Arup and Partners Hong Kong Ltd.
Main Contractor Meinhardt (M&E) Ltd.
Description of Works

ACMV installation consists of sea water cooled centrifugal chiller plant totalled 8500 tonnes and screw type air cooled chiller plant totalled 250 tonnes.

Electrical installation consists of 3,200A LV switchboards, standby / emergency generators with rating from 750 kVA to 1,500 kVA, UPS public address, SMARTV / BRI and emergency call bell system.

Fire Services installation consists of fire hydrant and hose reel, automatic sprinkler, automatic fire detection and alarm, FM 200 Gaseous Extinguishing System, Total Flooding System and pre-action systems.

Plumbing and Drainage installation consists of potable water supply, cleansing water supply, grey water, soil and waste disposal and rain water disposal (underground and above ground).